
The Sheringham Shoal Offshore Wind Farm is a significant renewable energy project located off the coast of Norfolk, England. It's situated about 16 kilometers off the coast.
The farm spans an area of approximately 220 square kilometers, making it one of the largest offshore wind farms in the world. It's a massive project, to say the least.
The wind farm consists of 103 turbines, each with a capacity of 3.6 megawatts. That's a lot of wind power!
A fresh viewpoint: Pacific Coast Steamship Company
Construction
Construction of the Sheringham Shoal Offshore Wind Farm began in 2009, with onshore work starting that year and offshore construction beginning in March 2010.
Nexans was awarded a €24m contract to supply and construct the 145kV export cables in April 2008, and another contract in April 2009 to supply 81 km of 36kV inter-array cables.
The offshore substations were designed and project managed by Wood Group, which was subcontracted by Areva, who obtained a €50 million contract to supply the substations in late 2008.
Take a look at this: American Recovery and Reinvestment Act of 2009
Ramboll was contracted to design the turbine and substation foundations, while MT Højgaard supplied the foundations for the substations and 88 turbines.
The manufacture of turbine monopiles and transition pieces was subcontracted to Sif Group and Smulders, and the substation superstructure and foundations were subcontracted to Heerema, Bladt Industries, and Sif Group and Smulders.
Siemens obtained a €450 million contract to supply 88 wind turbines to the wind farm in 2009.
Export cable installation began in late 2010, under contract to Visser & Smith Marine Contracting, with the ships Atlantic Guardian, Team Oman, and VOS Sympathy carrying out the work.
The first turbine was installed on 3 July 2011, and began generating electricity in August 2011.
Installation of the remaining foundations and transition pieces was complete by August 2011, with Seaway Heavy Lifting carrying out the work using the Oleg Strashnov vessel.
Turbine installation was carried out by Gulf Marine Services, with the initial contract with Master Marine being terminated due to delays.
The wind farm became fully operational in late summer 2012, after installation of all the turbines was complete.
A unique perspective: Ural Turbine Works
Operation
The Sheringham Shoal Offshore Wind Farm was operational by late 2011, and it officially opened on September 27, 2012, with a visit from Norway's Crown Prince Haakon and UK Secretary of State Ed Davey.
The cost of developing this massive wind farm was estimated at 10 billion Norwegian krona, which is equivalent to $1.8 billion. This significant investment paid off, as the wind farm quickly became a notable contributor to the UK's renewable energy efforts.
By June 2013, the electrical transmission assets of the wind farm were acquired by a consortium called Blue Transmission for £193 million. This deal marked a significant shift in the ownership and management of the wind farm.
Statkraft took over operations and maintenance of the wind farm from Scira in August 2013, and then Statoil took over operation from Statkraft in 2017, while also increasing its share in the proposed Dogger Bank Wind Farm.
The wind farm generated 1.2 TWh in its first year of operation, which is a remarkable feat considering the scale of the project. Its levelised cost has been estimated at £150/MWh, a figure that reflects the efficiency and effectiveness of the wind farm's design and operation.
Curious to learn more? Check out: Vending Machine Took My Money
Project Details
The Sheringham Shoal Offshore Wind Farm is an impressive project with some remarkable details. The wind farm consists of 88 turbines, each with a capacity of 3.6MW.
The turbines are quite tall, standing at 80m high, with three 52m long blades. Each turbine is mounted on a tubular steel monopile that's driven 23-37m into the seabed.
The monopiles themselves are massive, weighing between 375 to 530 tonnes and ranging in length from 44m to 61m. On top of the monopile, a 22m-long transition piece is mounted, weighing around 200 tonnes.
The offshore infrastructure of the wind farm includes two 900-tonne substations, which are connected to the turbines via 132kV marine cables. These cables make landfall at Weybourne, where they're connected to the onshore substation.
The onshore substation is located near Cawston, and it feeds the power to the local 132kV UK Power Networks distribution network. From there, the power is transported to the national grid.
By generating power from the wind farm, the project helps reduce carbon dioxide emissions by 500,000 tonnes annually.
On a similar theme: Harman Connected Services
Cost and Contracts
The cost of building the Sheringham Shoal offshore wind farm was significant, with a €60m contract signed with Statoil in 2008 for the supply of two offshore substations and a gas-insulated onshore substation.
AREVA was awarded this contract, which also included the supply of transformers, circuit breakers, and reactive power compensation. The total cost of this contract was €60m, which is equivalent to approximately $88.1m.
Wood Group Engineering (North Sea) was subcontracted by AREVA to design two offshore stations, adding another layer of expertise to the project.
Nexans was awarded a €24m contract in April 2008 to supply 22km of submarine export cables, spare cable, and equipment, as well as an optical-fibre cable.
Total Cost
When you're considering a contract, it's essential to factor in the total cost. The total cost of a contract can be broken down into several components, including the initial cost, ongoing costs, and potential costs of disputes or terminations.
Related reading: When Are Product Costs Matched Directly with Sales Revenue
The initial cost of a contract can be substantial, with some contracts requiring significant upfront payments or investments. For example, a construction contract may require a down payment of 10% to 20% of the total project cost.
Ongoing costs, such as maintenance and repair expenses, can also add up over time. In the case of a software contract, the ongoing costs may include subscription fees, support costs, and potential upgrade fees.
Potential costs of disputes or terminations can be significant and should not be overlooked. A contract dispute can result in costly legal fees, while a contract termination can result in significant penalties or losses.
In some cases, the total cost of a contract can be influenced by external factors, such as changes in market conditions or regulatory requirements. For instance, a contract for a project that requires specialized labor may become more expensive if there is a shortage of skilled workers in the area.
It's crucial to carefully review and understand all the costs associated with a contract before signing. By doing so, you can make an informed decision and avoid costly surprises down the line.
Worth a look: Upside Potential Ratio
Plant Contracts
AREVA was contracted to supply major equipment for the Sheringham Shoal offshore wind farm, including transformers, circuit breakers, and reactive power compensation, under a €60m contract signed with Statoil in 2008.
This contract was part of a larger deal that included the supply of two offshore substations and a gas-insulated onshore substation. Wood Group Engineering (North Sea) was subcontracted by AREVA for designing two offshore stations.
Nexans, a cable company, was awarded a €24m contract in April 2008 to supply 22km of 145kV cross-linked polyethylene submarine export cables, spare cable and equipment and an optical-fibre cable. The company received another €12m ($15.8m) contract in April 2009 to supply 81km of infield cables and equipment.
MT Højgaard supplied 90 offshore foundations for the turbines and two substations. Siemens Energy supplied turbines under a €450m ($597m) contract won in 2009.
Nexans was contracted for power export cables, infield cables, and ancillary equipment, while Carillion Utility Services received the order to deliver onshore cables.
Related reading: 2009 Supervisory Capital Assessment Program
Environmental and Location
The Sheringham Shoal Offshore Wind Farm is located between 17km and 23km off the coast of North Norfolk in the UK.
The site is situated around 5km north of the offshore sand bank known as Sheringham Shoal, and has a relatively shallow water depth ranging between 17m and 22m.
A detailed biodiversity assessment was conducted to evaluate the project's potential impact on marine and terrestrial habitats, as well as mammals, birds, fish, and benthic fauna.
Environmental Aspects
The Environmental Aspects of offshore wind farms are a crucial consideration. By virtue of its technical characteristics, this project is classified as an Annex II-project according to the EIA-Directive 85/337/EEC, as amended.
National legislation requires a full EIA including public consultation for offshore wind farms. EIA was conducted including a detailed biodiversity assessment, covering marine and terrestrial habitat, mammals, birds, fish and benthic fauna.
The assessment aimed to minimize the impact on the environment. The approval was granted by the competent authority following extensive public consultation.
Readers also liked: Ubs Culture Match Assessment
Location Details
The Sheringham Shoal Offshore Wind Farm is located in a unique spot, between 17km and 23km off the coast of North Norfolk in the UK.
The site is situated around 5km north of the offshore sand bank known as Sheringham Shoal.
Water depth in this area is relatively shallow, ranging from 17m to 22m.
The site of the project is a diamond shape, spread over an area of 35km.
Broaden your view: Commerce Web
Features
The Sheringham Shoal Offshore Wind Farm has a prime location, allocated by the UK Government in 2004. This spot offers excellent conditions for wind energy production, with favorable wind speeds, suitable water depth, minimal fishing activity, and easy access.
The wind farm boasts an impressive 88 turbines, each with a capacity of 3.6MW. The turbines have three long blades, measuring 170ft, mounted at a height of 262ft.
The turbines can automatically start operating at a wind speed of 3-5m/s and continue to produce energy until the wind speed reaches 13-14m/s. If the average wind speed exceeds 25m/s, the turbines will stop operating to prevent damage.
A different take: Net Operating Cash Flow
The safety system is designed to reset automatically when the wind speed drops below the restart speed, ensuring the turbines can resume operation safely.
The turbines are connected to offshore substations using two types of infield cables, one being a 27kg/m cable, which is 26km long, and the other an 18kg/m cable, measuring 56km in length.
You might like: Patricia Lopez / Bloomberg Opinion
Grid and Market
The Sheringham Shoal Offshore Wind Farm has a grid network that's connected to both the regional and national grids, thanks to agreements with UK-based energy companies EDF Energy and National Grid Transco.
Wind power is a significant player in the UK's energy market, with an installed capacity of 5GW as of mid-2011.
The UK's wind power capacity has been growing rapidly, with wind energy overtaking hydroelectricity in 2007 to contribute 2.2% of the total electricity consumption in the UK.
As of 2010, the UK had 500MW of onshore and 653MW of offshore wind farms, with wind energy expected to grow further due to its low costs and urgent need to address CO2 emissions.
The development of onshore and offshore wind farms is predicted to deliver 30% of the country's electricity supply and decarbonise the economy by 2020.
Frequently Asked Questions
Who owns Sheringham Shoal Offshore Wind Farm?
The Sheringham Shoal Offshore Wind Farm is owned by Equinor, Green Investment Group, and TRIG, holding a combined 74.7% stake, with Equitix managing funds holding a 25.3% interest.
Featured Images: pexels.com


